Hello There, hope all are fine.
Here I’ve attached how a factory maintain Time & Action
for Product delivery. Please be informed it’s created TNA but contained are
almost same. 
| 
   
TNA 
 | 
 |||||
| 
   
Buyer 
 | 
  
   
 Li & Fung 
 | 
  
   
Rib Fab Content 
 | 
  
   
95% Ctn 5% Spandex 
 | 
  
   | 
 |
| 
   
Order #  
 | 
  
   
JA-2376 
 | 
  
   
Rib Fab GSM 
 | 
  
   
190 GSM 
 | 
  
   | 
 |
| 
   
Style # 
 | 
  
   
Boys -S6 
 | 
  
   
Rib Consumption per Dz 
 | 
  
   
200 gm 
 | 
  
   | 
 |
| 
   
Item # 
 | 
  
   
Crew neck tee 
 | 
  
   
Total Rib Req 
 | 
  
   
4500 Kg 
 | 
  
   | 
 |
| 
   
Body Fabric Content # 
 | 
  
   
100% Ctn 
 | 
  
   
Yarn Count 
 | 
  
   
24/S 
 | 
  
   | 
 |
| 
   
Body Fab Knitting Pattern # 
 | 
  
   
S/J 
 | 
  
   
Spandex 
 | 
  
   
40D 
 | 
  
   | 
 |
| 
   
Body Fab GSM # 
 | 
  
   
170 GSM 
 | 
  
   | 
  
   | 
  
   | 
 |
| 
   
Gmts Ord Qty in pcs # 
 | 
  
   
240000 
 | 
  
   
Machine Dia to be used 
 | 
  
   
24 .28.30.34 
 | 
  
   | 
 |
| 
   
Ord Confirmation Date # 
 | 
  
   
6/8/2010 
 | 
  
   
Yarn Count 
 | 
  
   
28/5 
 | 
  
   | 
 |
| 
   
Del Date/ TOD # 
 | 
  
   
 6-0ct 
 | 
  
   | 
  
   | 
  
   | 
 |
| 
   
Body Fab Consumption per Dz # 
 | 
  
   
 
  3.00 Kg 
 | 
  
   
Finished fab requirement 
 | 
  
   
60000 Kg 
 | 
  
   | 
 |
| 
   
Color/Qty 
 | 
  
   
 S 
 | 
  
   
M  
 | 
  
   
L 
 | 
  
   
XL  
 | 
  
   
Total 
 | 
 
| 
   
Pink 
 | 
  
   
10000 
 | 
  
   
20000 
 | 
  
   
20000 
 | 
  
   
10000 
 | 
  
   
60000 
 | 
 
| 
   
Olive 
 | 
  
   
10000 
 | 
  
   
20000 
 | 
  
   
20000 
 | 
  
   
10000 
 | 
  
   
60000 
 | 
 
| 
   
Brown 
 | 
  
   
10000 
 | 
  
   
20000 
 | 
  
   
20000 
 | 
  
   
10000 
 | 
  
   
60000 
 | 
 
| 
   
Aqua  Blue 
 | 
  
   
10000 
 | 
  
   
20000 
 | 
  
   
20000 
 | 
  
   
10000 
 | 
  
   
60000 
 | 
 
| 
   
Total
   
 | 
  
   
40000 
 | 
  
   
80000 
 | 
  
   
80000 
 | 
  
   
40000 
 | 
  
   
240000 
 | 
 
| 
   
SI No Events 
 | 
  
   | 
  
   | 
  
   
Action Date 
 | 
  
   
Remarks 
 | 
 |
| 
   
1 
 | 
  
   
Cargo must be at ctg
  port by 
 | 
  
   
6-0ct 
 | 
  
   | 
 ||
| 
   
2 
 | 
  
   
Cargo must leave factory not later than 
 | 
  
   
5-0ct  
 | 
  
   
Truck, Cover Van 
 | 
 ||
| 
   
3 
 | 
  
   
Final insp to be offered not later than 
 | 
  
   
3-0ct 
 | 
  
   | 
 ||
| 
   
4 
 | 
  
   
finishing must be completed not later than 
 | 
  
   
2-0ct 
 | 
  
   | 
 ||
| 
   
5 
 | 
  
   
All Washing (if any) must be completed not later than 
 | 
  
   
1-0ct 
 | 
  
   | 
 ||
| 
   
6 
 | 
  
   
All Sewing must be completed not later than 
 | 
  
   
30-Sep 
 | 
  
   | 
 ||
| 
   
7 
 | 
  
   
Bulk Production as per target must be achieved not later than 
 | 
  
   
31-Aug 
 | 
  
   
All Fab& Acey 
 | 
 ||
| 
   
8 
 | 
  
   
Input Should begiven in required lines to achieve day's Target prod not later than 
 | 
  
   
30-Aug 
 | 
  
   | 
 ||
| 
   
9 
 | 
  
   
Emb for day's prod
  qty must be in house not later than (if any emb) 
 | 
  
   
29-Aug 
 | 
  
   | 
 ||
| 
   
10 
 | 
  
   
Printing for day’s tgt qty must be rcvd from printing not later than 
 | 
  
   
28-Aug 
 | 
  
   | 
 ||
| 
   
11 
 | 
  
   
Cutting should be done for required day's production as per ratio not later than 
 | 
  
   
27-Aug 
 | 
  
   | 
 ||
| 
   
12 
 | 
  
   
Size-set and PP must be approved not later than 
 | 
  
   
24-Aug 
 | 
  
   | 
 ||
| 
   
13 
 | 
  
   
All Lob-Test which may affect shipment to be completed not later than 
 | 
  
   
30-Sep 
 | 
  
   | 
 ||
| 
   
14 
 | 
  
   
Dyed fabric as per size/col ratio for day's production must be delivered to cutting not late 
 | 
  
   
26-Aug 
 | 
  
   | 
 ||
| 
   
15 
 | 
  
   
Knitted Fabric for day's prod as
  per size color ratio must be delivered to cutting not later 
 | 
  
   
22-Aug 
 | 
  
   | 
 ||
| 
   
16 
 | 
  
   
Knitting for day's garments production (as per ratio) must start not later than 
 | 
  
   
19-Aug 
 | 
  
   | 
 ||
| 
   
17 
 | 
  
   
Yarn must be at factory for day's targeted qty
  not later than 
 | 
  
   
17-Aug 
 | 
  
   | 
 ||
| 
   
18 
 | 
  
   
BB L/C for yarn must be opened not later than 
 | 
  
   
15-Aug 
 | 
  
   | 
 ||
| 
   
19 
 | 
  
   
Master L/C  must be received from Buyer not later than 
 | 
  
   
11-Aug 
 | 
  
   | 
 ||
| 
   
20 
 | 
  
   
Color Standard Must be received not later than 
 | 
  
   
7-Aug 
 | 
  
   | 
 ||
| 
   
21 
 | 
  
   
first Lab dip to be submitted not later than 
 | 
  
   
10-Aug 
 | 
  
   | 
 ||
| 
   
22 
 | 
  
   
Product package must be received not later than 
 | 
  
   
7-Aug 
 | 
  
   | 
 ||
| 
   
23 
 | 
  
   
Proto Sample must be submitted not later than (with available Fabric) 
 | 
  
   
8-Aug 
 | 
  
   | 
 ||
| 
   
24 
 | 
  
   
All Accessories Development must be completed and approved not later than 
 | 
  
   
16-Aug 
 | 
  
   | 
 ||
| 
   
25 
 | 
  
   
All Accessories must be at factory not later than 
 | 
  
   
27-Aug 
 | 
  
   | 
 ||
| 
   
26 
 | 
  
   
All washing approval (if any) must be obtained by 
 | 
  
   
2-Sep 
 | 
  
   | 
 ||
| 
   
27 
 | 
  
   
Sewing and Thread Must be at factory by 
 | 
  
   
28-Aug 
 | 
  
   | 
 ||
| 
   
28 
 | 
  
   | 
  
   | 
  
   | 
 ||
| 
   
29 
 | 
  
   | 
  
   | 
  
   | 
 ||
| 
   
30 
 | 
  
   | 
  
   | 
  
   | 
 ||
| 
   
31 
 | 
  
   | 
  
   | 
  
   | 
 ||
| 
   
32 
 | 
  
   | 
  
   | 
  
   | 
 ||
Comments