Hello There, hope all are fine.

Here I’ve attached how a factory maintain Time & Action for Product delivery. Please be informed it’s created TNA but contained are almost same.


TNA
Buyer
 Li & Fung
Rib Fab Content
95% Ctn 5% Spandex

Order #
JA-2376
Rib Fab GSM
190 GSM

Style #
Boys -S6
Rib Consumption per Dz
200 gm

Item #
Crew neck tee
Total Rib Req
4500 Kg

Body Fabric Content #
100% Ctn
Yarn Count
24/S

Body Fab Knitting Pattern #
S/J
Spandex
40D

Body Fab GSM #
170 GSM



Gmts Ord Qty in pcs #
240000
Machine Dia to be used
24 .28.30.34

Ord Confirmation Date #
6/8/2010
Yarn Count
28/5

Del Date/ TOD #
 6-0ct



Body Fab Consumption per Dz #
  3.00 Kg
Finished fab requirement
60000 Kg

Color/Qty
 S
M
L
XL
Total
Pink
10000
20000
20000
10000
60000
Olive
10000
20000
20000
10000
60000
Brown
10000
20000
20000
10000
60000
Aqua  Blue
10000
20000
20000
10000
60000
Total
40000
80000
80000
40000
240000
SI No Events


Action Date
Remarks
1
Cargo must be at ctg port by
6-0ct

2
Cargo must leave factory not later than
5-0ct
Truck, Cover Van
3
Final insp to be offered not later than
3-0ct

4
finishing must be completed not later than
2-0ct

5
All Washing (if any) must be completed not later than
1-0ct

6
All Sewing must be completed not later than
30-Sep

7
Bulk Production as per target must be achieved not later than
31-Aug
All Fab& Acey
8
Input Should begiven in required lines to achieve day's Target prod not later than
30-Aug

9
Emb for day's prod qty must be in house not later than (if any emb)
29-Aug

10
Printing for day’s tgt qty must be rcvd from printing not later than
28-Aug

11
Cutting should be done for required day's production as per ratio not later than
27-Aug

12
Size-set and PP must be approved not later than
24-Aug

13
All Lob-Test which may affect shipment to be completed not later than
30-Sep

14
Dyed fabric as per size/col ratio for day's production must be delivered to cutting not late
26-Aug

15
Knitted Fabric for day's prod as per size color ratio must be delivered to cutting not later
22-Aug

16
Knitting for day's garments production (as per ratio) must start not later than
19-Aug

17
Yarn must be at factory for day's targeted qty not later than
17-Aug

18
BB L/C for yarn must be opened not later than
15-Aug

19
Master L/C  must be received from Buyer not later than
11-Aug

20
Color Standard Must be received not later than
7-Aug

21
first Lab dip to be submitted not later than
10-Aug

22
Product package must be received not later than
7-Aug

23
Proto Sample must be submitted not later than (with available Fabric)
8-Aug

24
All Accessories Development must be completed and approved not later than
16-Aug

25
All Accessories must be at factory not later than
27-Aug

26
All washing approval (if any) must be obtained by
2-Sep

27
Sewing and Thread Must be at factory by
28-Aug

28



29



30



31



32