Hello There, hope all are fine.
Here I’ve attached how a factory maintain Time & Action
for Product delivery. Please be informed it’s created TNA but contained are
almost same.
TNA
|
|||||
Buyer
|
Li & Fung
|
Rib Fab Content
|
95% Ctn 5% Spandex
|
|
|
Order #
|
JA-2376
|
Rib Fab GSM
|
190 GSM
|
|
|
Style #
|
Boys -S6
|
Rib Consumption per Dz
|
200 gm
|
|
|
Item #
|
Crew neck tee
|
Total Rib Req
|
4500 Kg
|
|
|
Body Fabric Content #
|
100% Ctn
|
Yarn Count
|
24/S
|
|
|
Body Fab Knitting Pattern #
|
S/J
|
Spandex
|
40D
|
|
|
Body Fab GSM #
|
170 GSM
|
|
|
|
|
Gmts Ord Qty in pcs #
|
240000
|
Machine Dia to be used
|
24 .28.30.34
|
|
|
Ord Confirmation Date #
|
6/8/2010
|
Yarn Count
|
28/5
|
|
|
Del Date/ TOD #
|
6-0ct
|
|
|
|
|
Body Fab Consumption per Dz #
|
3.00 Kg
|
Finished fab requirement
|
60000 Kg
|
|
|
Color/Qty
|
S
|
M
|
L
|
XL
|
Total
|
Pink
|
10000
|
20000
|
20000
|
10000
|
60000
|
Olive
|
10000
|
20000
|
20000
|
10000
|
60000
|
Brown
|
10000
|
20000
|
20000
|
10000
|
60000
|
Aqua Blue
|
10000
|
20000
|
20000
|
10000
|
60000
|
Total
|
40000
|
80000
|
80000
|
40000
|
240000
|
SI No Events
|
|
|
Action Date
|
Remarks
|
|
1
|
Cargo must be at ctg
port by
|
6-0ct
|
|
||
2
|
Cargo must leave factory not later than
|
5-0ct
|
Truck, Cover Van
|
||
3
|
Final insp to be offered not later than
|
3-0ct
|
|
||
4
|
finishing must be completed not later than
|
2-0ct
|
|
||
5
|
All Washing (if any) must be completed not later than
|
1-0ct
|
|
||
6
|
All Sewing must be completed not later than
|
30-Sep
|
|
||
7
|
Bulk Production as per target must be achieved not later than
|
31-Aug
|
All Fab& Acey
|
||
8
|
Input Should begiven in required lines to achieve day's Target prod not later than
|
30-Aug
|
|
||
9
|
Emb for day's prod
qty must be in house not later than (if any emb)
|
29-Aug
|
|
||
10
|
Printing for day’s tgt qty must be rcvd from printing not later than
|
28-Aug
|
|
||
11
|
Cutting should be done for required day's production as per ratio not later than
|
27-Aug
|
|
||
12
|
Size-set and PP must be approved not later than
|
24-Aug
|
|
||
13
|
All Lob-Test which may affect shipment to be completed not later than
|
30-Sep
|
|
||
14
|
Dyed fabric as per size/col ratio for day's production must be delivered to cutting not late
|
26-Aug
|
|
||
15
|
Knitted Fabric for day's prod as
per size color ratio must be delivered to cutting not later
|
22-Aug
|
|
||
16
|
Knitting for day's garments production (as per ratio) must start not later than
|
19-Aug
|
|
||
17
|
Yarn must be at factory for day's targeted qty
not later than
|
17-Aug
|
|
||
18
|
BB L/C for yarn must be opened not later than
|
15-Aug
|
|
||
19
|
Master L/C must be received from Buyer not later than
|
11-Aug
|
|
||
20
|
Color Standard Must be received not later than
|
7-Aug
|
|
||
21
|
first Lab dip to be submitted not later than
|
10-Aug
|
|
||
22
|
Product package must be received not later than
|
7-Aug
|
|
||
23
|
Proto Sample must be submitted not later than (with available Fabric)
|
8-Aug
|
|
||
24
|
All Accessories Development must be completed and approved not later than
|
16-Aug
|
|
||
25
|
All Accessories must be at factory not later than
|
27-Aug
|
|
||
26
|
All washing approval (if any) must be obtained by
|
2-Sep
|
|
||
27
|
Sewing and Thread Must be at factory by
|
28-Aug
|
|
||
28
|
|
|
|
||
29
|
|
|
|
||
30
|
|
|
|
||
31
|
|
|
|
||
32
|
|
|
|
Comments